Project: I-39 Kishwaukee River Bridge Location: Rockford, Illinois Salespersons:Jim Becker, Frank Varak
Scope: 100,000 square feet
This is an Illinois Department of Transportation project.
It is approximately 100,000 square feet for both the northbound and southbound bridge.
Products:
MEADOW-PATCH® 20 Fast Setting, General Purpose Cementitious Repair Mortar MEL-DEK™ Deck Waterproofing System MEL-PRIME™ Solvent-Based VOC Primer POINTING MASTIC Cold-Applied, Single-Component Polymeric Sealing Compound
Project: SeaTac North Satellite Rail Tunnel
Port of Seattle (International Airport)
Product:REZI-WELD® LV Epoxy
Epoxy injection - Pumped between
100 and 200 psi.
Epoxy was kept at a constant temperature of 102 degrees. Pump
had heaters on each resin reservoir.
Project: Confederation Bridge, Concrete
Curing
New Brunswick to Prince Edward
Island
13 kilometers, design life - 100 years
Reinforced, post-tensioned concrete