| 07 13 26 |
|
Click
here for:
|
DESCRIPTION
MEL-DEK is a roll-type waterproofing membrane composed of a nominally
53 mil thick layer of polymeric waterproofing membrane on a shrink-resistant,
heavy-duty, 12 mil thick polypropylene woven carrier fabric. The two components
are laminated together under strictly controlled production procedures.
USES
MEL-DEK Waterproofing System provides an excellent waterproofing membrane for
bridges, parking decks or other vehicular traffic structures to be overlaid
with an asphalt concrete wearing course. MEL-DEK is ideal for repair, maintenance
or new construction applications.
|
PACKAGING
60’ (18.29 m) Long x 38.5” (.98 m) Wide Rolls
COVERAGE
180 sq. ft. net (16.72 sq. m) of effective waterproofing coverage. (192.5 gross
coverage.)
SPECIFICATIONS
ASTM D 6153, Type III
PHYSICAL PROPERTIES
| Thickness | 65 mils |
| Tensile Strength,
ASTM D 882 Warp Fill |
90
lbs./in. (1.6 kg/mm) 90 lbs./in. (1.6 kg/mm) |
| Elongation, ASTM
D 882 Polymeric Membrane Fabric, Warp Fabric, Fill |
410% 35% 45% |
| Puncture, ASTM E 154 | 275 lbs. (122 kN) |
| Flexibility, ASTM
D 146 180º Bend, 1/4" (6.35 mm) mandrel @ -26º F (-32º C) |
PASS |
| Water Vapor Permeance, ASTM E-96, Water Method |
0.03 Perms |
| Water Absorption, ASTM D 1970 ASTM D 1228 |
0.06% 0.06% |
| Independent test report available upon request | |
APPLICATION
Note:
For applications receiving overlays other than asphalt, please consult with
W. R. MEADOWS Technical Service.
Surface Preparation ... New concrete surfaces are to be fully cured and dry or approved by the engineer. Surface is to be cleaned of all dust, dirt and debris just prior to priming. Existing concrete surfaces are to have a smooth, sound, monolithic surface, free of voids, spalled areas, sharp protrusions and loose aggregate. Remove all traces of old membranes, oil, grease or other contaminants. For enhanced bond between asphalt overlay and MEL-DEK, apply an asphalt emulsion, water-base tack coat to the surface of MEL-DEK.
Temperature ... MEL-DEK may be applied in fair weather at air and concrete surface temperatures of 40° F (4° C) and higher.
Joints and Slab Drainage
... Apply a reinforcing strip of W. R. MEADOWS DETAIL STRIP over all non-working
joints or cracks over 3/16” (4.76 mm) wide before applying finished membrane.
Seal all terminations with POINTING MASTIC from W.
R. MEADOWS. Deck surface must provide proper pitch to gutters and drains. Drainage
openings should be provided at the structural deck level to drain any water
that penetrates the asphaltic concrete surface.
Priming
... Prime all surfaces to be covered with MEL-PRIME
or MEL-PRIME W/B primer from W. R. MEADOWS. Primer
may be spray-applied or applied with a lamb’s wool roller. Allow primer
to dry until tack-free. Primed areas not covered in 24 hours must be re-primed.
Coverage: 250 to 300 sq. ft/gal. (6.14 to 7.36 sq. m/ L)
Application Method … Apply MEL-DEK from low point to high point in both the longitudinal and transverse directions. In the transverse direction, overlap in shingle fashion 2 ½” (63.5 mm) after removing the white polyethylene strip that exposes the 3/4” rubberized asphalt. This will give you the membrane-to-membrane weld at seams. Longitudinally, overlap 6” (150 mm) and seal with POINTING MASTIC. Once positioned, MEL-DEK should be immediately hand rubbed onto the surface, followed by a pressure-applied roll pressing of the complete surface to assure positive adhesion. Seal all terminations with POINTING MASTIC.
NOTE ... Where
a 125+ mil thick membrane is desired, overlap each roll of MEL-DEK 51%.
Inspect and Repair
... Inspect thoroughly before covering and make any necessary repairs immediately.
Patch all tears ... slit fish mouths and patch ... seal edges of all patches
with POINTING MASTIC.
Paving ... Placement of the asphalt concrete overlay should be accomplished as soon as possible after application of MEL-DEK. A minimum 2” (50 mm) compacted overlay thickness is required. The temperature of the asphalt concrete at the time of compaction should be a minimum of 290º F, not to exceed 340º F. Paving equipment should be rubber track variety. Protect the membrane surface from unnecessary traffic. Place the overlay from low point to high point with care and caution.
PRECAUTIONS
Refer to Material Data Safety Sheet for complete
health and safety information.
This material last updated March 2007.