This document has been created as an addendum to our AIR-SHIELD technical data sheets to provide information regarding the recommended treatment of joints in exterior sheathing panels (drywall and glass-faced) when using AIR-SHIELD LMP fluid-applied membrane.
Following are the typical installation instructions recommended by W. R. MEADOWS. However, it is important to review each application as there may be situations that may require this procedure to be modified based on the project requirements. If this situation arises, please contact W. R. MEADOWS Technical Service.
INSTALLATION INSTRUCTIONS
EXTERIOR SHEATHING PANELS
1 . Install and fasten exterior sheathing panels according to the sheathing manufacturer’ s instructions.
2. When installing the fasteners, ensure that they are driven flush with the surface (not countersunk) and into the framing. Any fasteners that are countersunk, or any holes from the removal of a fastener, must be pretreated with AIR-SHIELD LIQUID FLASHING prior to application of AIR- SHIELD LMP.
3. Inspect the joint to ensure that all areas to receive joint treatment are clean, dry, smooth, and free from all bond-breaking contaminants.
4. Remove and replace any damaged structural wall components.
JOINT TREATMENT USING AIR-SHIELD LMP FLUID-APPLIED MEMBRANE
1 . Fill joint area with AIR-SHIELD LMP using a W. R. MEADOWS SPREADER TOOL or a 3″ (76.2 mm) putty knife. A standard 3″ (76.2 mm) roller can be used to apply AIR-SHIELD LMP.
2. Extend AIR-SHIELD LMP beyond the joint line 3″ (76.2 mm) onto face of exterior sheathing.
3. Fully embed REINFORCING FABRIC HCR from W. R. MEADOWS 3″ (76.2 mm) wide into wet AIR-SHIELD LMP centered over the joint.
4. Run the SPREADER TOOL or putty knife over the embedded REINFORCING FABRIC HCR to remove any air bubbles.
2020-08