Project Name: Bay Division Pipeline at Hayward Vault
Location: Fremont, California, USA
Architect: San Francisco Public Utilities Commission
Contractor: Watertight Restoration, Inc.
Salesperson: Patrick Raney
Product: BEM
MEL-ROL®
PRECON®
Scope: 26,500 square feet
The project consists of roughly 6500 SF of PRECON that goes under the base slab of the articulating vault. This vault is designed to encase water supply pipes and is situated directly over the Hayward fault line. Once the vault is poured, MEL-ROL was used to waterproof roughly 20,000 SF of the exterior of the vault. The vault is designed to move in an earthquake.